2023 DPW Street Resurfacing Program Tentative Schedule (UPDATE)
As part of the Street Resurfacing Project, DPW crews plan to perform asphalt milling Carter Rd from West North Street to Angelo Street this Friday 8-11-23. Work will begin at 7:00 AM and continue until about 3:30PM or as needed. Traffic will be reduced to one lane while work is being performed. Motorists are encouraged to find alternate routes as necessary.
Please find tentative schedules below that may affect your neighborhood or commute. Work will consist of milling off the existing surface course and then paving hot mix asphalt . Milling is the process of grinding off the top layer of asphalt or surface of a roadway. Resurfacing is the process of placing an asphalt overlay onto a roadway. The milling and paving process is noisy and may cause discomfort and disruption in the affected neighborhoods.
Although DPW takes steps to minimize the inconveniences, this work requires dump trucks and special machinery and will include traffic disruptions.
Additional work in these areas may include, structure adjustments, concrete sidewalk ramps, and pavement marking installations.
**NOTE** Schedules are subject to change due to inclement weather, emergencies, conflicts and or breakdowns. We thank everyone in advance for your patience while we work to improve our streets. If you have any questions please call our engineering office at 315-789-3101 or feel free to use our complaints@geneva.ny.us email.
August 8: Mill- Carter Rd from West North St to Angelo St
August 7 – 8: Mill - Sweeney, Hawkins, MLK and Goodman
August 9: Mill - Virginia and Gate Ave
August 10: Mill – Hillcrest Ave and Maxwell Ave
August 11: Mill- Hillside Dr and Hampton Pl
August 14: Mill – Jeannette and Emily
August 15: Mill – Atwood Ave and Oxford Pl
August 16: Mill - Carter Rd Forge Ave and Doran Ave
August 17: Mill – Forge Ave and Doran Ave
August 18: Mill – Make up any areas
August 21-23: Pave - Forge Ave and Doran Ave
August 24: Pave - Sweeney, Hawkins, MLK and Goodman
August 25: Pave - Virginia and Gates Ave
August 28: Pave - Carter Rd
August 29: Pave - Maxwell Ave
August 30: Pave - Hillcrest Ave
August 31: Pave - Hillside Dr and Hampton Pl
September 1: Pave - Oxford and Atwood – Make up any areas